Before You Pour a Pole Barn Slab, Put the Pipe In
Before you pour a pole barn slab, lay every pipe you might ever want in it. An Ohio carpenter building a 24x36 barn on a tight budget did that with radiant heat tubing, water lines, and a bathroom drain, and he openly says he may never use any of them.
That isn't waste. It's the cheapest decision in the whole build, and it's the one you only get to make once.
The barn, briefly
It's a pole building on 6x6 pressure-treated posts set in concrete. The posts carry a beam that runs all the way around, and the roof sits on that beam.
He started a year before the video. He dug the holes and got it mostly framed, then sprained his ankle and lost about six months. By mid-October he was racing winter, and the barn still isn't finished. He walks through it anyway, including what he wouldn't repeat.
What went under the concrete
Here's what he put in before the slab was poured:
- PEX tubing for radiant floor heat. A friend came over one evening and the two of them laid it in a couple of hours. The pipe cost a few hundred dollars.
- Water lines run through the slab to where he expects to need them.
- A drain for a toilet and a sink. He describes the cost as a few dollars' worth of pipe and a little time.
- A gap. He deliberately kept pipe out of the corner where a two-post car lift might go, and that corner got extra-thick concrete with rebar.
None of it is hooked up. The tubing ends under the stairs, where a tankless water heater or a boiler could be mounted later to push hot water through the floor.
Radiant heat is easy to add before the pour and close to impossible after it. His words are blunter: if you decide you want it down the line, you're kind of out of luck.
That's the whole argument for roughing in. The pipe is cheap. The concrete over it isn't coming back up.
Why the lift corner matters
Keeping tubing out of a lift corner isn't fussiness. A post lift is bolted down through the slab, and you don't want to be drilling anchor holes over a pressurized water line.
Whether you need thicker concrete there is a separate question. Lift manufacturers publish a minimum slab spec for each model, and the owner who built the same shop twice built his second barn mainly because his first slab couldn't take one. This owner calls the lift a pipe dream. He prepped for it anyway.
Heat now, heat later
The floor heat is the long-term plan. For this winter, he hung a wall-mounted natural gas heater that he says cost a couple hundred dollars.
He had a free wood stove available and turned it down. It would have taken floor space, and he doesn't cut wood steadily enough to feed it. He's also realistic about the building: with two large garage doors, he expects much of the heat to escape no matter what heats it.
The roof: rafters instead of trusses
Most pole barns get trusses. A standard truss has a flat bottom chord, so you get a flat ceiling. Scissor trusses buy back some headroom.
He's a carpenter by trade, knows how to cut rafters, and didn't want to spend the money on trusses. So he framed the roof with 2x6 rafters, checked his spans, and tied the walls together with 2x6 collar ties. Those ties do a real job: load on the roof pushes the walls outward, and the ties hold them in.
With 12-foot walls, he has about 16 feet from the slab to the bottom of the collar ties. That height paid for a storage loft at one end, framed in 2x8 joists under 3/4-inch plywood and hung off a 24-foot triple LVL.
He also paid extra for high-lift garage doors, which he flags as an expensive option. A standard door rolls back flat at the top of the wall. His run up the wall and then follow the roof pitch, so the doors don't steal the ceiling space he built the rafters to get.
How the budget actually held
The biggest saving wasn't a technique. His brother is a general contractor, and the lumber yard he buys from calls him when it has damaged stock, such as plywood with an end nicked by a forklift. He can buy it by the pallet at a discount.
Through him, the owner bought four bunks of lumber that covered about 85% of his framing. He still had to buy the posts and purlins. The leftovers framed almost the entire loft.
There's no total in the video, and we won't guess one. If you want a budget build with every receipt attached, this one-man build set out to spend $15,000 and landed at $19,449.
What he'd rather not repeat
He's candid about three compromises:
- Insulation. He planned to hire out spray foam. The ankle injury meant hiring out the siding instead, and that spent the spray foam budget. What he has is 1.5-inch foam board between the purlins, another layer outside, and spray foam in the corners. Roughly 3 inches, and he says plainly it isn't perfect.
- Bedrock. His barn sits at the low end of a lot that slopes to the road. He planned to dig in and drain the uphill side, then hit bedrock about 8 inches down. Instead of chipping it out, he filled the low side with almost 2 feet of compacted recycled concrete and poured on that. If you're still at this stage, site prep is where these surprises belong.
- The retaining wall. His dad runs a garage door company, so he used salvaged insulated door panels, spanned post to post and screwed to a garage door reinforcement truss. He says he wouldn't recommend it to anyone. It was cheap, it was quick, and it solved the problem in front of him.
What's left: trenching for power, gas, and water in one dig, gutters front and back, and the ceiling insulation, which had to wait until the slab was poured so a scissor lift could roll in. For now the whole barn runs on extension cords from the house.
Decide what the floor might need. Put the pipe in. Then pour.
Frequently asked questions
Should I put radiant floor heat in a pole barn slab?
If there's any chance you'll want it, lay the tubing before the pour. The Ohio owner in this video did exactly that without committing to the heat itself. He spent a few hundred dollars on PEX and a couple of hours one evening with a friend, then poured over it. He may never connect a boiler, but the option exists. Adding the tubing after the concrete is down isn't really an option.
What should I rough in before pouring a pole barn floor?
This owner did three things: PEX tubing for radiant floor heat, water lines run through the slab, and a drain for a toilet and sink. He also left one corner clear of pipe where a car lift might be anchored someday. All of it is cheap before the pour and expensive after it.
Can you heat a pole barn without radiant floor heat?
Yes. This owner hung a wall-mounted natural gas heater that he says cost a couple hundred dollars, as a stopgap until he decides on the floor heat. He's honest that it won't be perfect: with two large garage doors, he expects a lot of the heat to leak out.
Rafters or trusses for a pole barn roof?
Trusses with a flat bottom chord give you a flat ceiling. This owner, a carpenter, cut his own 2x6 rafters with collar ties instead, because he wanted the height and didn't want to pay for trusses. On a 24x36 with 12-foot walls, that left about 16 feet from the slab to the collar ties and room for a storage loft.
What if you hit bedrock when digging a pole barn pad?
This owner hit bedrock about 8 inches down at the low end of a sloped lot. Rather than chip it out, he built the low side up with almost 2 feet of compacted recycled concrete and poured the slab on top. He calls the result not ideal, but it's what the site allowed.